Project Description
This Project consisted of improving reliability of electrical service to the Disneyland Resorts and California Adventure Park by upgrading and replacing aging equipment.
Our Role
Johnson-Peltier was contracted to install a Disney California Adventure Site Wide 12kV Cable Upgrade including an addition to the 5kV Switchgear and install (3) new 12kV Switching Stations for the Central Energy Plant at the Anaheim, CA facility. All work was performed within the confines of the Hotels and Cast Member areas, with limited shutdowns to the Hotels and Park. All work was accomplished in the time frame set forth by the client.
Johnson-Peltier procured and installed: (3) 12kV Switching Station Upgrade and Expansion, PMH and ATS Switches, Over 2,000’ Duct Bank & (6) Vaults, SCADA System Installation, 12kV Cable Pulling and Termination, Commissioning of Switch Stations